COMPLETED Projects

Projects

Below is an overview of completed projects, if you require any more information please feel free to contact us.

  • 132kv Sudkabel Terminations Pokeno Substation New Zealand

  • 66kv Sudkabel Terminations Cudgen Zone Substation Essential Energy

  • 66kv Terminations Jemalong Solar Farm

  • 11kv Terminations Sydney East Substation Transgrid

  • Ichthys LNG Gas Plant Emergency Repairs and Shutdowns

  • 330kv QNI Construction Transgrid

  • 33kv works Bluegrass Solar Farm

  • 3 x 33kv Substations Stockyard Hill Windfarm

  • 33kv works Biala Windfarm

  • 33kv works Kiamal Zone Substation

  • 33kv works Darlington Point Solar Farm Substation

  • 33kv fault location Darling Downs Solar farm

  • 33kv works Limondale Solar Farm. Substation and Solar farm

  • Lincolns Gap Wind Farm Port Augusta. Subcontracting works, 33kv Terminations

  • June 2018 to November 2018. Bodangora Wind Farm. Subcontracting works, 33kv Terminations

  • Jan 2018 to January 2019. Willogoleche Wind Farm. Subcontracting works, 33kv Terminations

  • Jan/Feb 2018 Longreach QLD Solar Farm. Subcontracting works, 66kv Terminations

  • Oct/Nov 2017 Kerang Victoria Solar Farm. Subcontracting works, 33kv Teminations

  • 2016/2017. Ichthys LNG Plant Darwin. 132kv and 33kv Terminations

  • Oct 2015 Subcontracting works at Roma QLD installing new 66kv cable and fitting 132 kv out door NKT composite terminations for Ergon at the Roma zone substation

  • September 2015 Subcontracting works at Roma QLD removing old terminations and fitting 132 kv out door NKT composite terminations for Ergon at the Roma zone substation

  • August 2015 Subcontracting works at Darwin on Cox Peninsula feeder cable fitting ABB 132kv out door terminations

  • May 2015 / July 2015 Ongoing Subcontracting works at Broken Hill Solar farm New South Wales, 33kv cable jointing works and VLF testing of all circuits.

  • Febuary2015 to May 2015 Subcontracting works at the Bald Hills wind farm Inverloch Victoria, 33kv cable jointing works connecting and testing cables to wind turbines.

  • November2014/February 2015 Subcontracting works at Nyngan Solar farm New South Wales, 33kv cable jointing works and VLF testing of all circuits.

  • October /November 2014 Subcontracting works Keysbough Zone Substation Victoria 66 kV jointing works for new United Energy feeder cables. Fitting Pfisterer GIS plug in 66 kV Terminations

  • October 2014 Subcontracting works at the Portland wind farm Victoria, 33kv cable jointing works connecting wind turbines.

  • July 2014 to September 2014 Subcontracting works at the Bald Hills wind farm Inverloch Victoria, 33kv GIS cable jointing works at New Substation fitting NKT 33kv GIS Plug in terminations.

  • June 2014 Subcontracting works Mackay QLD 66kv jointing works for new Ergon feeder cable. Fitting NKT 66kv STJ

  • February 2014 to May 2014 Subcontracting works at the Snow town wind farm South Australia, 33kv cable jointing works connecting wind turbines.

  • January 2014 Subcontracting works Grosvenor QLD fitting of 20 Pfisterer size 4 GIS 66kv terminations and associated testing works

  • December 2013 Subcontracting works Kadina Substation South Australia emergency cable repairs to 2 circuits of 66kv cables using CCC terminations

  • October 2013 to November 2013 Subcontracting cable jointing works Francis Bay Zone sub Darwin NT ,terminate 2 circuits of Sudkable 170kv GIS Terminations, terminate 2 x 170 kv ABB outdoor terminations ,Install 3 x 170 kv ABB straight joints

  • October 2013 Subcontracting cable jointing works, QR rail Moranbah QLD (Watonga Site) terminate 8 single circuits of 66kv cable including outdoor terminations and GIS Pfisterer indoor terminations

  • September 2013Subcontracting cable jointing worksQR rail Moranbah QLD (Carambadowns site)Works Terminate 4 circuits of 66kv cable including outdoor terminations and GIS Pfisterer indoor termination

  • September 2013 Subcontracting cable jointing works BHP Billiton Collie site WA for Emergency Maintenance Remove cracked 3 x 132 kV oil Oxisil terminations from transformer and replace with 3 NKT KEVT 170kv terminations

  • September 2013 Subcontracting cable jointing works Cadia Gold Mine Orange NSW for Emergency Maintenance, test locate and repair 4 sheath faults on the 7km 132kv cable circuit

  • August 2013 Subcontracting cable jointing works QR rail Brisbane QLD (Springfield site) Works Terminate 2 circuits of 66kv cable including outdoor terminations and GIS Pfisterer indoor termination

  • April 2013 to August 2013 Subcontracting cable jointing works Transpower New Zealand 220kv new feeder cable Penrose to Newmarket. Works fitting of NKT straight joints at joint bays 2,3,4,5 & 6

  • April 2006 to April 2012

Company Country Energy

Position Sub transmission Team leader cable works

Accountabilities

  • Resource Management and supervision

  • Project planning ,development and management

  • Tender preparation

  • Contract administration

  • Subcontractor analysis and recommendation

  • Project cost variances reports on projects

  • Design input and estimating on projects

  • Purchasing of all specialist jointing kits and products

  • All cable installation works and jointing works

 

Associated Works during this period

 

February 2012 Trackstar alliance project Umolo Qld

Terminate 8 x GIS 66kv cables in QR substation at Umolo

 

January 2012 Trackstar alliance project Blackwater Qld

Terminate 8 x GIS 66kv cables in QR substation at Blackwater

 

December 2011 CCPM (Ergon Energy) New St George Zone sub project

Terminate and Test (VLF) 6 circuits of 33kv ug cables

 

November 2011 Trackstar alliance project Duaringa Qld

Terminate 20 x GIS and 20 outdoor 66kv cables in QR substation at Duaringa

 

October 2011/April 2012 Ballina Zone Works

Commenced works to, install, Terminate and test dual circuit 66kv ug cables from TX to cable stand, install 1 circuit of 132kv from Canal Rd to Zone sub Ballina , installation and terminating of 1 circuit temporary 66 kv by pass cables

 

June/September 2011 3 Chain Rd dual circuit feeder cables

Install, terminate and test 3km dual circuit 66kv ug cables from 3 Chain Rd Zone sub to South Lismore Zone sub Union St Lismore

 

June Beryl Zone Sub

Install, terminate and test 240 metre circuit 66kv ug FI plant cables from Zone sub to Transgrid termination pole in Transgrid yard Beryl

 

May 2011 Sino Power Station (Desalination Plant) Works Western Australia

Position Cable Jointer

Works involved  the installation of 6 x 245kv indoor GIS terminations, 6 x 245kv TX oil terminations and 3 x 245kv of outdoor terminations

 

April 2011 Maclean feeder cable Transgrid Sub Grafton

Install, terminate and test 340 metre circuit 132kv ug feeder cables from Zone sub to Transgrid cable structure in Transgrid yard

 

April 2011 Kadina substation South Australia

Terminate 6 x 66kv cables in ETSA Substation Kadina

 

Feb 2011 Trackstar alliance project Roma St Brisbane

Terminate 6 x GIS 132 kV cables in QR substation

 

Jan 2011 Trackstar alliance project Darra QLD

Install and Terminate 9 x GIS 66kv cables in QR substation

 

December 2010 South Tamworth Zone Sub

Install, terminate and test 180 metre circuit 66kv ug feeder cables from Zone sub to Transgrid termination pole in Werris Creek Rd

 

November 2010 Co Generation Plant Condong Sugar Mill

Routine maintenance found that all 66kv termination (12 in total) had substantial tracking on the stress cone.

Arranged emergency outage to replace all 12 terminations, sourced all materials and worked on site to replace.

 

October 2010 South Tamworth Zone Sub

 

Install, terminate and test dual circuit 66kv ug cables to FI plant 1 & temporary busbar feeder cables

September 2010 Oaks Zone Sub Queanbeyan

 

Install, terminate and test dual circuit 66kv ug cables to FI plant 1 & 2

Procurement of all materials for works

 

May 2010 to July 2010 Sino Power Station Works Western Australia

Position Cable Jointer

Works involved the installation of 15 x 245kv indoor GIS terminations and 15 x 245kv of outdoor terminations

 

January 2010 to May 2010 Transgrid Substation Koolkhan

Install, terminate and test dual circuit route length 400 metres 66kv underground cables from substation to termination poles in Boral timber Yards Summerland Way Koolkhan

 

February 2010 Stroud Rd Substation

Install, terminate and test 13 circuits of 33kv underground cables in and out of Stroud Rd substation.

 

Jan 2010 Terranora Rd Zone Substation

Installation of the 66kv sub transmission neutral reactor cable, the associated jointing works and testing

 

October 2009 /December 2009 South West Rock

Conduit and joint pit installation for future 4.5km dual circuit 66kv

Supervision of contractor Lucas Stewart

 

September 2009/ Armidale Zone Sub

Install, terminate and test single circuit route length 200 metres 66kv underground cables from Miller St substation to Miller St & Mossman Road Termination Pole

 

June 2009/ Boambee Zone

Install, terminate and test Single circuit 360 metres 66kv underground cables from Transgrid substation to Deans Rd Termination Pole

 

May2009/ MacLean Zone sub

 

Install, terminate and test Single circuit 120 metres (Temporary cables) 66kv underground cables from TX bar to Termination Pole

 

March 2009/ Dec 2009 Cable replacement Forster /Tuncurry Bridge

Single circuit route length 1300 metres 66kv underground cables from Termination Pole Tuncurry side of Bridge to termination Pole Memorial Drive Forster

Supervised & worked onsite carrying out;

Cable tray design works

Specialised roller design works to fit cable tray

Procurement of all materials for works

Installation of the sub transmission cables, the associated jointing works and testing

 

March 2009 to Dec 2009 Terranora Zone Sub

Works, removal of 2 x 110kv sub transmission towers with 2 circuits of 110kv under cable

Supervised & worked onsite carrying out;

Procurement of all materials for works

Installation of the sub transmission external feeder cables on hold, the associated jointing works and testing on hold as well.

 

March 2009/ Glenn Inness

Install, terminate and test single circuit 120 metres 66kv underground cables from Glenn Inness sub to FI plant

 

Feb 2009/ March 2009 Koolkhan Transgrid substation

Install, terminate and test single circuit route length 375 metres 66kv underground cables from Transgrid sub to Mill Road Termination Pole

 

January / February 2009 Stroud Road substation

Install, terminate and test single circuit (temporary cables) 300 metres 66kv underground cables from substation to Termination Pole with in sub yard

 

November/ December 2008 Lismore Uni

Install, terminate and test dual circuit, route length of 3km 66kv underground cables from Skyline Drive to Military road Zone substations

 

July/October 2008 South Tweed Heads

Install, terminate and test dual circuit, route length of 2.4 km of 66kv underground cables, from the new zone substation in Sunshine Avenue, to the corner of the old highway and Parry St South Tweed.

April/June 2008 Martins Creek

Install ,terminate and test single circuit 3.3 km 33kv circuit from Vogel St to Martins Creek new Zone substation & Siemens GIS 33kv switch board terminations 18  in total

February /May 2008 Oxley vale Zone substation Tamworth

Install, terminate and test triple circuit .route length 500 metres of 66kv underground cables from Oxley vale substation to termination poles in horse paddock in unnamed lane.

 

October /December 2007 Dungog Zone Substation

Install, terminate and test 3 circuits, route length 500 metres of 33kv cable from new Dungog Zone GIS substation across Stroud Rd to 3 termination poles in cow paddock.

Supervised & worked onsite carrying out;

 

April 2006 to November 2007 Continuation on Tweed Heads stages 1 to 14

Major Sub transmission system augmentation

 

  • Resource Management and supervision

  • Project planning ,development and management

  • Tender preparation

  • Contract administration

  • Subcontractor analysis and recommendation

  • Project cost variances reports on projects

  • Design and estimating on projects

  • Purchasing of all specialist jointing kits and products

 

April 2006 to August 2006 network conversion from overhead to under ground in Grafton CBD

  • Resource Management and supervision

  • Project planning ,development and management

  • Purchasing of all specialist jointing kits and products

  • Testing and commissioning works 11kv works only

 

 

 

Nov 2001 to April 2006

Company Country Energy

Position Under Ground Construction Project  Team Leader

Accountabilities

  • Resource Management and supervision

  • Project planning ,development and management

  • Tender preparation

  • Contract administration

  • Subcontractor analysis and recommendation

  • Project cost variances reports on projects

  • Design and estimating on projects

  • Purchasing of all specialist jointing kits and products

  • All cable installation works and jointing works

 

Associated Works during this Period

 

To April 2006

 

Currently working on the South Grafton substation, sub transmission cables and the Foster bridge sub transmission cable relocation project

 

October 2005 to December 2005 Wagga Zone substation Wagga Wagga  

Install, terminate and test 4 circuits of 66 kV cables, 4.2 km of cable

Supervised & worked onsite carrying out;

 

August 2005/September 2005 Boronia Street Substation Port Macquarie

 

Install, terminate and test 3 circuits of 33kv cable 6km of cable installed

Supervised & worked onsite carrying out;

 

June 2005 /July 2006 Kempsey Zone

Install, terminate and test 5 circuits of 33kv underground cable

Supervised & worked onsite carrying out;

 

March 2005 to May 2005

Install, terminate and test temporary 66kv sub transmission cables at the following substations

Cudgen, Lismore and Mullumbimby  

 

February 2004 Foster Zone Substation

Install terminate and test 2 x 66kv sub transmission external feeder cables.

 

April 2003/April 2006 Tweed Heads major Sub transmission system augmentation

Install terminate and test all 66kv underground cable works for stages 1 to 14 (24km of cable)

Banora Point Works, Terranora Zone substation and New Cudgen No 2 sub

4 x 66 kV underground circuits out of Terranora Zone Sub (12kms of cable)

3 x 66 kV underground circuits of cable out of Banora Point substation (10km of cable)

4 x 66 kV underground circuits of cable from new GIS room (2km cable)

 

August 2002 to December 2002 network conversion from overhead to under ground in Tweed Heads CBD

  • Resource Management and supervision

  • Project planning ,development and management

  • Purchasing of all specialist jointing kits and products

  • Testing and commissioning works 11kv works only

 

  • May 2002 June 2002 Clearwater Zone Substation Port Macquarie

Install terminate and test 2 circuits of 33 kv from substation to Ocean Drive termination Poles

 

March 2002 Byron Bay lighthouse Project, convert overhead power to underground power, while maintaining access for visitors and the National Parks and Wildlife Services to the light house. Completed project was praised by local news and media highlighting the visual change to the general area with the removal of the overhead wires.

 

Secondment to Major Project’s Group

November 1998 to November 2001

Report to General Manager Major Projects

Accountabilities

  • Resource Management and supervision

  • Project planning ,development and management

  • Estimation and review of project tenders

  • Tender preparation and submission

  • Contract administration

  • Financial forecasting on tended projects

  • Strategic planning and analysis

  • Subcontractor analysis and recommendation

  • Carried out all emergency fault works on Direct link project

 

Associated Works during this period

 

June 2001 to December 2001 network conversion from overhead to under ground in Ballina CBD

  • Resource Management and supervision

  • Project planning ,development and management

  • Purchasing of all specialist jointing kits and products

  • Testing and commissioning works 11kv works only

 

February 2001 to July 2001 network conversion from overhead to under ground in Port Macquarie CBD

  • Resource Management and supervision

  • Project planning ,development and management

  • Purchasing of all specialist jointing kits and products

  • Assisted with testing and commissioning works 11kv works only

 

August 2000 to December 2000 Mac Gettigans Lane Ewingsdale 132kv under ground cable replacement 1km of overhead dual pole construction

Install terminate and test of the sub transmission cables, the associated jointing works, testing and commissioning

August 2000 to May 2001 Cudgen satellite substation to Hastings Point substation 66kv sub transmission project

Installation, jointing, testing and commissioning of the 7km circuit

Works received a commendation from the National Parks and Wildlife Service as works along the beach front were contained a SEPP 26 rainforest.

 

June 2000/Dec 2000 Murray link project

Selected as the construction project manager as part of the tender submission team on this project.

 

 September 1999/ June 2000 Secondment to Kilpatrick Green as the site cable laying and cable jointing supervisor for the Direct link Project.

This was the first dc construction type project of its type in Australia and my works involved,

  • The supervision of the 6 circuit 65km long 88kv dc cables, and the installation of over 365 inline joints and 36 cable terminations.

  • Partially Supervised the installation of 110kv ac cable from Bungalora Zone substation to Terranora zone substation

  • Supervised 132kv Mullumbimby & 132kv 3 Chain Rd Testing and commissioning works

 

 

 

Nov 1998 to August 1999 White horse Council OH to UG Project Melbourne Vic

Undergrounding the overhead power, Telstra, Optus and Foxtel services along 3.3 kilometres each side of The Maroondah highway including Mitcham CBD

Works included;

  • Cable TV relocation

  • Telstra relocation

  • Optus relocation

  • Installation of sub transmission cable ,22kv cables and low voltage cables

  • Installation of Pad mount substations

  • Resupply 400 houses via underground power

  • Resupply 160 commercial industrial buildings via underground power

  • The contract allowed for no more than 1 hour power interruptions

  • Most works were done by live line methods

  • Spent 7 months onsite as project manager

 

1997 Mercury Energy OH to UG Project

North Power tender bid submission team in New Zealand, as the underground construction manager.

 

October 1996 to Nov1998

Secondment by Network General Manager to set up underground construction and maintenance working crew’s across the all the North Power region’s

Position: Underground Construction Manager North Power

Reported to Design and construction manager NorthPower

Accountabilities

  • Set up teams to carry out underground construction works in 8 separate locations

  • Sized these teams to meet the work loads of each location

  • Produced standard work practices, tools, and equipment for each team

  • Arranged standard fleet and plant for each team

  • Produced a quality manual for use within and without the North Power franchise area

Supervised the following

  • UG subdivisions excavating and cable installation up to 66kv

  • High rise and commercial industrial projects, high voltage power installation

  • All cable jointing works on the NorthPower Network

  • Substation construction works including commissioning

  • High voltage equipment installation

  • Updating schematic diagrams of the new electrical network

  • Arranged all tradesmen, plant and materials to meet customer requirements on their project

  • Provided weekly works programmes to all staff

  • Carried out fault finding maintenance and repairs to the NorthPower network

  • Assisted the Design and Construction manager in quoting all major projects and reviewed costing ( actual costs V estimated costs) when works were completed

  • Key achievements

  • Maintained 10% profit margin on all works, turn over from the 28 man team was 6 million dollars per annum

  • Achieved all safety and environmental requirements to allow NorthPower the ability to achieve the 5 star safety award as well as the ISO 14001 environmental accreditation

Oct 1995 to May 1996

Company North Power

Reported to Regional Network Manager Central

Position Distrubution Manager Central

 

Accountabilities

Supervised the Following staff and functions at 4 separate locations;

  • On call Electrical Technicians

  • Zone substations Technicians

  • Underground construction workers

  • The system control room in Coffs Harbour

  • Provided weekly works programme for the above

 

Key achievements

Supervised the successful relocation of the system control room from Coffs Harbour to Port Macquarie

No LTI

 

Feb 1985 to Oct 1995

 

Company: Northern Rivers County Council

Reported to Special Projects Officer

Positions

1990 to 1995

Foreman of Underground Construction and maintenance works Southern Region

 

Accountabilities

Supervised the following

  • High rise and commercial industrial projects, high voltage power installation

  • All cable jointing works and cable testing on the NRCC Network up to 66kv

  • Substation construction works including commissioning

  • High voltage equipment installation

  • Updating schematic diagrams of the new electrical network

  • Arranged all tradesmen, plant and materials to meet customer requirements on their project

  • Provided weekly works programmes to all staff

  • Carried out fault finding maintenance and repairs to the NRCC network

  • Assisted the special projects officer in quoting all major projects and reviewed costing ( actual costs V estimated costs) when works were completed

 

Feb 1988 to Feb 1990

Company: Northern Rivers County Council

Reported to Special Projects Officer

Positions

1988 to 1990

Leading hand Electrical fitter cable jointer

 

Company: Northern Rivers County Council

Reported to Foreman of Underground Construction and maintenance works Southern Region

Position

1988

Reclassified as leading hand Electrical fitter cable jointer

 

Company: Northern Rivers County Council

Reported to Leading Hand

Positions

1985 to 1988

Cable Jointer

 

Accountabilities

Preformed the following duties

  • All cable jointing works including cable testing on the NRCC Network up to 66kv

  • High rise and commercial industrial projects, high voltage power installation

  • Substation construction works including commissioning

  • High voltage equipment installation

  • Carried out fault finding maintenance and repairs to the NRCC network

  • System earthing

 

 

 

 

 

 

 

 

September 1978 to February 1985

 

Company: BHP

 

Position: Trade assistant 1978 to 1980

Position: Cable Jointer 1980 to 1985

 

Reported to: Electrical Maintenance & Construction Engineering Superintendent Generation  

Accountabilities

  • Overhead line construction to 132kv,maintenance and repair of lines up to 132kv

  • Substation construction ,maintenance and repair

  • Cable installation ,maintenance and repair of cable networks to 132kv

  • Cable Jointing high voltage to low voltage on new and maintenance projects

 

  • Worked on the following cables:

PILCSWA, HSL, MIND, CONSAC, Oil, Gas and pilot cables.

 

  • Trouble shooting on high and low voltage cable faults under extreme pressure to meet production schedules

Assessed competent on using the following fault finding equipment

 

BICC Pulse echo, BICC capacitive discharge tester and BICC cable locator

 

January 1977 to September 1978 Wonson Electrical Position Apprentice Electrician

Company closed on death of owner in September 1978